Abstract
The Status of the Richmond Vale Rail Trail.
Project Staging
To progress the design and the relevant environmental approvals the project has been divided into two sections, Shortland to Tarro and Hexham to Kurri Kurri. The staging of each Section is slightly different.
Section 1: Shortland to Tarro
The Status of the Richmond Vale Rail Trail.
Project Staging
To progress the design and the relevant environmental approvals the project has been divided into two sections, Shortland to Tarro and Hexham to Kurri Kurri. The staging of each Section is slightly different.
Section 1: Shortland to Tarro
The stages for Shortland to Tarro are as follows
Stage 1: Prepare concept design
Stage 2: Complete detailed design and prepare the Environmental Impact Statement (EIS) supported by the required environmental investigations.
Stage 3: Submit the design and EIS to the Department of Planning and Environment.
Stage 4: Public exhibition of EIS and acceptance of public submissions (min 30 days)
Stage 5: Review submissions and prepare submissions report
Stage 6: Determination by the Department
Stage 7: Design Review
Stage 8: Construction
We have approaching completion for Stage 2.
Section 1: Detailed Design and EIS
The detailed design is complete for the majority of the section, with the crossing the New England Highway is the major portion of design outstanding. The field work, investigations and report writing for the Environmental Impact Study has largely been completed and is currently being reviewed. NCC expects to release these documents for public exhibition in late 2017.
Originally the path started at the intersection of King and Mort St Shortland, moving North West along King St, going down the hill at the end of King St to enter the wetlands via a bridge across Ironbark Creek. The design has been revised to include universal access in Blanch St. The path from the Blanch St car park is for pedestrian and universal use only, it gives the pedestrian the choice of entering the Shortland Wetlands Centre or continuing along the path to join the main Shortland to Tarro Shared Path as shown in the Figure below.
Stage 1: Prepare concept design
Stage 2: Complete detailed design and prepare the Environmental Impact Statement (EIS) supported by the required environmental investigations.
Stage 3: Submit the design and EIS to the Department of Planning and Environment.
Stage 4: Public exhibition of EIS and acceptance of public submissions (min 30 days)
Stage 5: Review submissions and prepare submissions report
Stage 6: Determination by the Department
Stage 7: Design Review
Stage 8: Construction
We have approaching completion for Stage 2.
Section 1: Detailed Design and EIS
The detailed design is complete for the majority of the section, with the crossing the New England Highway is the major portion of design outstanding. The field work, investigations and report writing for the Environmental Impact Study has largely been completed and is currently being reviewed. NCC expects to release these documents for public exhibition in late 2017.
Originally the path started at the intersection of King and Mort St Shortland, moving North West along King St, going down the hill at the end of King St to enter the wetlands via a bridge across Ironbark Creek. The design has been revised to include universal access in Blanch St. The path from the Blanch St car park is for pedestrian and universal use only, it gives the pedestrian the choice of entering the Shortland Wetlands Centre or continuing along the path to join the main Shortland to Tarro Shared Path as shown in the Figure below.
Section 2: Hexham to Kurri Kurri
The stages for Hexham to Kurri Kurri, are as follows
Stage 1: Prepare concept design and prepare the Review of Environmental Factors supported by the required environmental investigations.
Stage 2: Assessment of the Design and REF by Cessnock City and Lake Macquarie City Councils.
Stage 3: Detailed Design Phase
Stage 4: Construction
We are approaching completion for Stage 1.
Concept Design and REF
The concept design is complete for the majority of the section. The access point at Dog Hole Rd, a road crossing and crossing Wallis and Surveyors Creeks are the outstanding design issues. There is a significant overlap between the documentation for the REF and the EIS, as with the EIS the field work, investigations and report writing for the Environmental Impact Study has largely been completed and is currently being reviewed. NCC expects to release these documents for public exhibition in late 2017.
The stages for Hexham to Kurri Kurri, are as follows
Stage 1: Prepare concept design and prepare the Review of Environmental Factors supported by the required environmental investigations.
Stage 2: Assessment of the Design and REF by Cessnock City and Lake Macquarie City Councils.
Stage 3: Detailed Design Phase
Stage 4: Construction
We are approaching completion for Stage 1.
Concept Design and REF
The concept design is complete for the majority of the section. The access point at Dog Hole Rd, a road crossing and crossing Wallis and Surveyors Creeks are the outstanding design issues. There is a significant overlap between the documentation for the REF and the EIS, as with the EIS the field work, investigations and report writing for the Environmental Impact Study has largely been completed and is currently being reviewed. NCC expects to release these documents for public exhibition in late 2017.
Presentation
The Status of the Richmond Vale Rail Trail
Presented on 27th September 2017 at the Active Transport: The Richmond Vale Rail Trail Conference (2017)